Data Center Construction Update

December 10th, 2009

Data Center Construction Update

I apologize for the delay here, but I've been quite busy lately and haven't had time to put together another data center update for our new site at 725 S Wells, here in Chicago.

This is the data from the report on Friday, Dec. 4:

7th Floor Construction Progress Summary:
Demolition: VCT tile, interior doors and Break Room cabinets removed, carpet removal in-progress.

8th Floor Construction Progress Summary:
Demolition: Overall space cleaned of debris. Bathroom demo complete except for plumbing. Existing HVAC units removed except for one on the North side. This will kept for temp heating. Suite entrance wall, doors and glass block window demolition in-progress.
Construction:
Painting: Concrete slab ceiling – removal of loose paint in-progress in preparation of painting.

Since then, all demolition has been completed, walls on the 7th floor are being prepared for painting and floors prepared for tile.  On the 8th floor, the ceiling has been prepared and painted and a final coating is being put on the concrete floors to smooth them out and to make them more durable.  Things are really progressing nicely at this point.

Here is a PDF with some pictures from Dec. 4th: http://steadfast.net/images/dec4progress.pdf

No feedback yet

Leave a comment


Your email address will not be revealed on this site.
(Line breaks become <br />)
(For my next comment on this site)
(Allow users to contact me through a message form -- Your email will not be revealed!)