Data Center Construction Report - Jan. 21

January 25th, 2010

Data Center Construction Report - Jan. 21

OK, I'm back on schedule.  I just got this report regarding progress as of Jan. 21 on Friday.

Basement Construction Progress Summary:
Existing Electrical Room: No ComEd shut down required. MDI Electric installed the bus detail “hot” in the existing 1600 amp switchgear. Building shutdown (load side) required and planned for January 30th to terminate cables.
Boiler Room: Demo of existing boilers and related piping complete.

7th Floor Construction Progress Summary:
Doors: Complete except card readers and elec. strikes.
Floors: Complete. Tile trim req. at suite door.
Voice/Data Security: Card reader and elec. strikes req.

8th Floor Construction Progress Summary:
Demolition: Complete.
Walls: Majority of gyp. Bd. Complete except toilets.
Doors/Windows: Office window frame installed, door frames on-site awaiting installation.
Floors: Raised floor laid-out over the underlayment
Ceilings: Uni-strut threaded rod installation in-progress.
Voice/Data Security: Voice/data wiring pulled from 7th floor to IDF Room.
Electrical: Roughing in primarily complete. Starline elect. Bus arrived and currently being loaded in building on the 4th floor.
Plumbing: Plumbing in-progress on 8th & 7th floors – drain lines & coring work.
Drain lines for the 8th floor toilets shall be ran o the 8th floor in lieu of 7th floor ceiling.
Fire Alarm: Not started.
Mechanical (Chilled water): Layout work in-progress (pumps, lines, CRAHs, etc...). Under access floor brackets installation in-progress.
Mechanical (Vent): Not started.

And here are the pictures: http://steadfast.net/images/jan21progress.pdf

No feedback yet

Leave a comment


Your email address will not be revealed on this site.
(Line breaks become <br />)
(For my next comment on this site)
(Allow users to contact me through a message form -- Your email will not be revealed!)