Data Center Construction Report - March 3
March 5th, 2010
Data Center Construction Report - March 3
Things are progressing nicely and looking great. It is definitely looking like a data center now.
General Building:
Dock: Temporary tap gen box installed.
Vertical Risers: Hogan ground boxes installed.
A/C condenser relocation: Condenser lines removed from future ComEd Vault.
Basement Construction Progress Summary:
Existing Electrical Room: Ground to water service in-progress.
Future Elec Room: Hogan Ground box installation in-progress
7th Floor Construction Progress Summary:
Tennant: Moved misc. equipment into 7th floor storage area.
Doors: Complete except card readers and elec. strikes.
Floors: Complete. Tile trim req. at suite door.
Voice/Data Security: Card reader and elec. strikes req.
Mechanical (Chilled water): Ready to core down to 6th floor.
8th Floor Construction Progress Summary:
Walls: Soffits at water cooler and IDF room near complete.
Doors/Windows: Rear window removed and readied for CRAH unit delivery.
Floors: Raised access floor primarily complete. Stairs primarily complete, awaiting handrails.
Ceilings: Uni-strut installation near complete.
Voice/Data Security: Installation of blue color pipe for Steadfast security and yellow for data in-progress.
Electrical: Wiring in-progress, PDUs arrived and set on stands.
Plumbing: Drain pan installed under overhead lines.
Fire Alarm: Fire alarm control panel installed.
Mechanical (Chilled water): Mech Room primarily complete, small lines left.
Mechanical (Vent): Office mech system near complete, humidistat install in-progress.
Sprinklers: Awaiting ceiling. Total Pac arrived.
Finishes: Primer and first coat paint complete.
Freight Elevator: Elevator cab, frame and curb raised and back in-service.
Miscellaneous: Interior roof steel installed for AHU-A.
Roof Construction Progress Summary:
Exterior: Exhaust fan and piping cores penetrations complete.
Interior: Elec room – 2 hr partitions complete awaiting door.
Elec: Ground box installed.
And the pictures: http://steadfast.net/images/march3progress.pdf