Data Center Construction Report - Feb.10
February 12th, 2010
Data Center Construction Report - Feb.10
Here is the construction report on the new data center from Feb. 10.
General Building:
Dock: Temporary tap gen box installed.
Vertical Risers: PDU feeds from 8th to 6th floor near complete.
A/C condenser relocation: Condenser platform installed – awaiting condensers.
Basement Construction Progress Summary:
Existing Electrical Room: Temporary electrical service complete; transformer not currently energized.
Future Elec Room: Transfer switch installed.
8th Floor Construction Progress Summary:
Walls: Majority of gyp. bd. complete.
Doors/Windows: Office window frame installed, door frames on-site awaiting
installation.
Floors: Raised floor laid-out over the underlayment. PDU & CRAH stands on-
site.
Ceilings: E/W Uni-strut installation complete.
Voice/Data Security: Installation of blue color pipe for Steadfast security and
yellow for data in-progress.
Electrical: New 400 amp panel mounted, installing switches and wall outlets.
Plumbing: Plumbing primarily complete, Hot water heater installed, new water
service riser and pumps on-hold.
Fire Alarm: Installation of red color conduit and in-progress
Mechanical (Chilled water): Chilled water line installation in progress primarily
the mechanical room, pumps arrived, lines installed to 7th floor.
Mechanical (Vent): Roof penetrations completed, fan coil units on-site, economizer ductwork in-progress.
Sprinklers: Turned pipe up, branch work and 2” wet main to office area in-
progress.
Finishes: Primer and first coat paint complete.
Miscellaneous: Temp freight elev and suite door installed. Mech conc housekeeping pads installed. Structural support for AHU-A penetration complete.
Roof Construction Progress Summary:
Exterior: Exhaust fan and piping cores penetrations complete.
Interior: Elec room – 2 hr partitions complete awaiting door.
Then, pictures: http://steadfast.net/images/feb10progress.pdf