Data Center Construction Report - March 10

March 17th, 2010
Sorry for the delay on this one, had been down in Austin for SXSW and just got back in. It was a great event, and hopefully I have the time to get a blog post together about it. General Building: Dock: Temporary tap gen box installed. Vertical Rise… more »

Steadfast Networks Announces Green Initiative Carbon Offset Hosting Services

March 9th, 2010
Leading dedicated server hosting provider, now certified CarbonFree, offers customers carbon offset hosting services. Chicago, IL (PRWEB) March 9, 2010 – Steadfast Networks, a leading Chicago based colocation services and dedicated server hosting prov… more »

Data Center Construction Report - March 3

March 5th, 2010
Things are progressing nicely and looking great. It is definitely looking like a data center now. General Building: Dock: Temporary tap gen box installed. Vertical Risers: Hogan ground boxes installed. A/C condenser relocation: Condenser lines rem… more »

Data Center Construction Report - Feb. 24

February 26th, 2010
Things are looking good and still seem to be on schedule for opening in early April. General Building: Dock: Temporary tap gen box installed. Vertical Risers: Hogan ground boxes installed. A/C condenser relocation: Condenser platform installed – aw… more »

Data Center Construction Report - Feb.10

February 12th, 2010
Here is the construction report on the new data center from Feb. 10. General Building: Dock: Temporary tap gen box installed. Vertical Risers: PDU feeds from 8th to 6th floor near complete. A/C condenser relocation: Condenser platform installed – a… more »